History

Efficient operation since 2009
2001

Development of the Ust Luga port begins

2006

Dredging works begin and the site of the terminal is constructed

spring 2007

Construction of the terminal is in full swing

autumn 2007

Construction of railway tracks is completed

spring 2008

Assembly of the shiploader begins

summer 2008

The warehouse is constructed and the portal reclaimer is assembled

autumn 2008

Construction of the wagon unloading station continues

spring 2009

Commissioning of the main equipment begins

summer 2009

First handling of bulk materials is performed

autumn 2009

The facility for sulfur handling is put into operation

Efficient
operation since 2009