History
Efficient operation since 2009
2001
Development of the Ust Luga port begins
2006
Dredging works begin and the site of the terminal is constructed
spring 2007
Construction of the terminal is in full swing
autumn 2007
Construction of railway tracks is completed
spring 2008
Assembly of the shiploader begins
summer 2008
The warehouse is constructed and the portal reclaimer is assembled
autumn 2008
Construction of the wagon unloading station continues
spring 2009
Commissioning of the main equipment begins
summer 2009
First handling of bulk materials is performed
autumn 2009
The facility for sulfur handling is put into operation